An aerial view of construction at the Great Plains Power Station project.

We started construction on March 15, 2021. See what we’ve accomplished up to November 2021 in this video:

Here’s our current schedule:

  • Break ground – Early 2021
  • Piling – Spring/Summer 2021
  • Foundations and Undergrounds – Summer/Fall 2021
  • Site goes vertical – Early 2022
  • Transmission line energized – Spring 2023
  • Power station in-service – 2024

Construction Progress

  • Spring 2022 – PCL Industrial starts erection of the Heat Recovery Steam Generator (HRSG).
  • Winter 2022 – Supreme Steel from Saskatoon begins steel erection of the powerhouse building and site goes vertical.
  • Fall 2021 – Allan Construction continues underground and foundation installations. Quorex Construction starts construction of the administration and water treatment plant building with Innovative Piling Solutions.   
  • Summer 2021 – Allan Construction began excavations and installation of underground pipe. Soletanche Bachy Canada (SBC) completed 50% of the piles. Inland Concrete from Moose Jaw supplies concrete for the Heat Recovery Steam Generator (HRSG) foundation.
  • Spring 2021 – Allan Construction started excavations and poured the foundation for the heat recovery steam generator sump. Soletanche Bachy Canada (SBC) starts piling activities.
  • Winter 2021 – Burns & McDonnell mobilized to site. Allan Ventures began site clearing and preparation activities.
  • Fall 2020 – Nekaneet First Nation blessed the site of the new power station. Watch the video below to learn more. KMS Construction Ltd. from Tuxford, SK completed road upgrades for SaskPower. KMS Construction also installed the first phase of the sanitary, water and storm infrastructure for the City of Moose Jaw.

Express Yourself

This page makes me feel:
icon-express-yourself-inspired% INSPIRED
icon-express-yourself-informed% INFORMED
icon-express-yourself-unsure% UNSURE
icon-express-yourself-annoyed% ANNOYED
icon-express-yourself-frustrated% FRUSTRATED