Where Work is Happening

This fall construction season, we’re beginning power line rebuilds in the following areas:

Power Line Rebuilds
 Area Kilometers of
Power Line 
Investment Completion
Date
 Assiniboia  23 km  $754,000  Nov. 2021
 Kipling  246 km  $8 million  Dec. 2021
 Moosomin  27 km  $902,000  Oct. 2021
 Prince Albert  20 km  $656,000  Dec. 2021
 Rosetown  30 km  $984,000  Oct. 2021
 Shaunavon  42 km  $1.3 million  Dec. 2021
 Sturgis  38 km  $1.2 million  Oct. 2021
 Unity  30 km  $984,000  Dec. 2021
 Weyburn  78 km  $2.6 million  Nov. 2021

 

In the summer of 2021, we began rebuilding power lines in:

  • Demaine area
  • Melaval area
  • South of Cedoux

Completion of the new lines is on track for the of fall 2021. These projects will ensure that these areas have reliable power for years to come.

Express Yourself

This page makes me feel:
icon-express-yourself-inspired% INSPIRED
icon-express-yourself-informed% INFORMED
icon-express-yourself-unsure% UNSURE
icon-express-yourself-annoyed% ANNOYED
icon-express-yourself-frustrated% FRUSTRATED